Municipal Projects
City of Vernon
Directional drilling below B.X. Creek on 25th Avenue for water main installation: field assessment, EMP, Section 11 WSA Notification, DFO Request for Review (Western Water Associated Ltd.).
48th Avenue Improvements: WSA Notification and Dewatering Management Plan (Western Water Associated Ltd.).
BX Creek Pipeline Repair: fish salvage, monitoring turbidity (Western Water Asscoaited Ltd.).
Tronson Road Lift Station Upgrades: EMP, WSA Notification, monitoring turbidity (Western Water Associated Ltd.).
Directional drilling for a watermain, stormwater outfall installation, and bank stabilization near B.X. Creek at 32nd Avenue: Danger Tree Assessment, EMP, Section 11 WSA Approval, DFO Request for Review (Western Water Associated Ltd.).
Permitting, reporting and environmental monitoring to support water main improvements along 43rd Ave and 24th St (Western Water Associated Ltd.).
Hurlburt Park Environmental Assessment and Environmental Monitoring for the City of Vernon. Working with project engineers, contractors and the City of Vernon Parks Planner to oversee construction work and provide environmental mitigation during trail construction, instream debris removal and ditching near the high water mark of Okanagan Lake in Vernon BC (Western Water Associates Ltd.).
Marshal Field Dog Park Environmental Assessment for the City of Vernon. Provided a literary review of dog use in public parks, species at risk assessment, site assessment and practical, environmentally-friendly recommendations to support off-leash dog use near Vernon Creek where it flows through Marshal Fields Park in Vernon BC (Western Water Associates Ltd.).
Three-year Vernon Creeks Baseline Monitoring Project for the City of Vernon. Project work involved collecting water quality, sediment quality and benthic samples seasonally, field water quality measurements monthly, and assessing flow measurements in Vernon and BX Creek annually over three years. Ten samples sites were routinely assessed and water samples were collected twice a year during storm events. Bacterial source tracking samples were collected monthly in 2018. WWAL wrote annual reports and a final report that presented the results of the study to City of Vernon Engineers and Officials. Results will be used to establish improved stormwater management solutions within city limits (Western Water Associates Ltd.).
Permitting, reporting and environmental monitoring to support water, sewer or storm main improvements along 35th Ave and Tronson Road (Western Water Asscoaited Ltd.).
City of Williams Lake, BC
Williams Lake River Valley Multiple Bridge and Slide Site Repair: EMP, WSA Approval, Scientific Fish Collection permit, DFO Authorization, DFO Offsetting Plan, silt fence installation, fish salvage, turbidity monitoring, pH monitoring during concrete pouring (Western Water Associates Ltd.).
Williams Lake aquatic plant sampling, western painted turtle trapping and reporting (Western Water Associates Ltd.) (Western Water Associates Ltd.).
Environmental monitoring during aquatic plant removal in Williams Lake (Western Water Associates Ltd.).
City of Armstrong
Meighan Creek Dredging: EMP, DFO Project Review, Section 11 Application, amphibian and fish salvage, environmental monitoring and compensation planting plan (Western Water Associated Ltd.).
Fortune Creek Water Supply Upgrades: EMP, DFO Project Review, Section 11 Application, environmental monitoring and compensation planting plan (Western Water Associated Ltd.).
SPEA setback determination along Deep Creek (Western Water Associated Ltd.)
Armstrong Watershed Managment Plan Coordination (Western Water Associated Ltd.).
Regional District of North Okanagan (RDNO), Vernon BC
Weir and Dam removal on B.X. Creek: EMP with fish habitat restoration plan, WSA Change Approval, Scientific Fish Collection permit, DFO Request for Review (Western Water Associates Ltd.).
Kalavisita Water Main Replacement: EIA, Dewatering Management Plan, placing sediment traps and monitoring dewatering discharge (Western Water Associates Ltd.)
Headgates Dam Improvements: EMP, Provincial Order, fish salvages, and compensation planting plan, environmental monitoring (Western Water Associates Ltd.)
Creekside Road Pumphouse Removal: Section 11 Approval, EMP and environmental monitoring (Western Water Associates Ltd.).
Weir and concrete removal on Coldstream Creek in Nobel Canyon: Section 11 Approval, EMP, DFO Project Review, Fish Salvage and environmental monitoring and compensation planting plan (Western Water Associates Ltd.).
Beaver Dam Removal from Coldstream Creek; silt curtain placement, vegetation management and sediment control (Tetra Tech).
Kalavista Lagoon Dredging at Kalavista Launch; turbidity monitoring (Associated Environmental).
Species at Risk Assessment to support the removal of an abandoned pumphouse in a sensitive grassland area (Western Water Associates Ltd.).
City of Salmon Arm, Salmon Arm BC
Reconstruction of Canoe Beach Park boat launch: EMP and Crown Land Tenure application (Western Water Associates Ltd.).
Shuswap Lake Sampling: monthly limnological sampling of Shuswap Lake by boat, depth profile, dissolved oxygen profile, zooplankton and phytoplankton sampling (Western Water Associates Ltd.).
Columbia Shuswap Regional District, BC
Pebble Beach Park Lake Access in Blind Bay BC: EMP, Section 11 Approval (Western Water Associates Ltd.).
Bristow Road Boat Launch in Celista, BC: Section 11 Approval, EMP, DFO Review, DFO Authorization Application and Offsetting Plan, Compensation Planting Plan and environmental monitoring managment (Western Water Associates Ltd).
Pedestrian Walkway along the Salmon River near Salmon Arm, BC: Section 11 Approval, EMP compensaiton planting plan and environmental monitoring (Western Water Associates Ltd.).
Swansea Point Fire Station Water Main Direction Drill: Section 11 Change Approval, EMP and environmental monitoring (Western Water Associates Ltd.).
Removal of a former weir and concrete pool in a Shuswap Lake Tributary, Swanse Point BC: Section 11 Change Approval, EMP, fish salvage and environmental monitoring (Western Water Associates Ltd.).
Squamish-Lillooet Regional District, Goldbridge, BC
Biophysical assessment, riparian plant survey, fish habitat assessment and multi-year water quality sampling and reporting to inform an Environmental Impact Study for upgrades to a wastewater treatment plant (Western Water Associates Ltd.).
Village of Cache Creek, BC
Compeltion fo a biophysical assessment, EMP, Section 11 Change Approval, DFO Project Review and environmental monitoring for debris removal in Bonaparte River (Western Water Associates Ltd.).
Taking flow measurements of Cach Creek and te Bonaparte River to inform a Flood Management Plan (Western Water Associates Ltd.).
Water quality sampling, biophysical assessment and riparian plant survey for an Environmental Impact Study for upgrades to a wastewater treatment plant.
City of Kamloops, BC
Dike Vegetation Management Plan for the City of Kamloops, Kamloops BC – Conducted an assessment of four dikes along the Thompson River as a part of a Dike Vegetation Management Plan. In the management plan, she provided recommendations on vegetation management along the dikes with the consideration of dike stability, public safety, and fish and wildlife habitat (Western Water Associates Ltd.).